Once your machine has actually been through testing at the institute, there's still one stage left before you get a report you can use for a subsidy claim or a tender: the Draft Test Report, or DTR.

It's a short but important checkpoint, and it's the last point where you, as the manufacturer, get formal input into the report before it's finalised. Here's how it fits into the overall sequence.

Where the DTR sits in the process

After your equipment has been received at the institute and a Test Engineer has been assigned, the actual testing happens — physical performance, endurance, safety checks, whatever the category requires. As results come in, the Test Engineer uploads intermediate results along the way.

Once testing is complete, the Test Engineer prepares the Draft Test Report. This isn't the final document — it's a working version that gets internal sign-off first. The institute's Admin reviews and approves the DTR before it goes anywhere near the manufacturer.

The comment window

Once the DTR is approved internally, it's shared with the manufacturer. This is your window to review the findings and submit comments — questions, clarifications, or objections to how something was recorded or tested.

Worth noting: the exact number of days allowed for this comment window isn't something we can state precisely here — it varies, so confirm the specific deadline with your institute when the DTR is issued to you. What matters is what happens with the comments once you've submitted them.

What happens to your comments

Your comments don't go straight back to the Test Engineer. They're submitted through the system, and the Admin forwards them on to the Test Engineer for examination. The Test Engineer then reviews what you've raised and, taking that into account, prepares the Final Test Report (FTR).

That sequence matters: comments get examined, not just filed. If there's a genuine discrepancy — a spec that was recorded incorrectly, for instance — this is the mechanism for catching it before the report becomes final and permanent.

After the Test Engineer prepares the FTR, the Admin examines it, then approves and releases it. At that point, the manufacturer receives the Final Test Report — the document you'll actually use for scheme eligibility, tenders, or general proof of performance.

What if you miss the comment window

The process is built around a linear, one-way flow: DTR issued, comments submitted, comments forwarded, FTR prepared. If the comment stage passes without a response from your side, there's nothing in the process that holds the report back waiting for you — the Test Engineer moves forward and prepares the Final Test Report based on the draft as it stands.

In practice, that means the DTR stage is your one real opportunity to flag something before it's locked in. Once the FTR is released, it's the official record. So it's worth treating the DTR review as a genuine checkpoint rather than a formality — read it carefully, check the figures against what you expected, and raise anything that looks off within whatever window the institute gives you.

Notifications at every step

One practical thing worth knowing: the system sends SMS alerts and email notifications to the applicant at every stage of the process, including when the DTR is ready for comment. That's useful, but it also means the responsibility sits with you to check those notifications and act promptly — a missed email is still a missed window.

What it looks like in a released report

The clearest way to understand the comment stage is to see what survives into the final document.

In a Commercial Test Report (Initial) we reviewed for a tractor-mounted, PTO-operated rotavator, the institute's summary raised two points for corrective action. The first was that the implement hitch specification conformed to the applicable three-point-linkage standard except on mast height, and should be looked into. The second was that the operator's manual, service manual and parts catalogue had been supplied in English only, and should also be produced in Hindi and other regional languages for the benefit of users and technical personnel.

The report then carries a numbered Applicant's Comments section, keyed to those two paragraphs. Against the first, the applicant recorded that the point was noted and would be looked into to meet the recommendation. Against the second, that the point was considered and material would be provided to suit customer state-wise requirements.

Three things are worth drawing out of that.

Your reply is printed, not just filed. It appears in the released report, under your name, alongside the institute's observation. It is a public commitment for as long as the report is valid.

The format is point-by-point. Comments are keyed to the institute's own paragraph numbers. A general letter of response doesn't fit the structure; a numbered reply to each recommendation does.

Accepting a point is a normal, and often correct, answer. Neither reply above disputed the finding. Where an observation is fair, acknowledging it and committing to act reads better than an argument — and disputing a finding you cannot substantiate is worse than accepting one you can fix.

Where this fits into the bigger picture

The DTR-to-FTR stage comes near the end of a longer chain: application, scrutiny, fee verification, sample allocation, testing, and only then the draft and final reports. If you're coordinating a test and want help understanding where you are in that sequence, or making sure documentation and comments are submitted correctly and on time, that's the kind of process navigation AgPro Consulting helps manufacturers with — guiding and liaising with the institute throughout, while the testing itself is always carried out by FMTTI's own engineers.

Start here

Have a question this post didn't answer?

WhatsApp us — we reply within one business day, free and no obligation.

Offices
Pune · New Delhi
Response time
One business day

Tell us about your machine.

We reply within one business day. Free, no-obligation guidance.

Free & no-obligation. One business day.